A 53-foot truck crashed into an industrial building, causing a section of the masonry wall to collapse right next to the machine that produces $400,000 worth of parts per day for a world-renowned manufacturing tenant. A 10-day production shutdown would have cost approximately $4 million. Bélisle rebuilt the wall exclusively at night, using a temporary electrical system, without ever interrupting factory operations.
Type of claim: Structural damage—vehicle impact against an exterior masonry wall
Sector: Industrial (commercial rental)
Scope: ~100 linear feet by 40 feet high of masonry to be replaced, adjacent electrical systems
Claim value: ~$100 000
Operational challenge: Tenant’s primary production equipment located directly against the affected wall—~$400,000 worth of parts produced per day, no downtime tolerable
1. Background
A 53-foot truck collided with a building owned by an industrial real estate manager, causing part of the exterior masonry wall to collapse. The loss is estimated at approximately $100,000: about 100 linear feet of wall, 40 feet high, needs to be replaced, in addition to the electrical panels and wiring located directly on that wall, on the interior.
A retained engineer quickly confirmed that the building’s structure was not affected: repairs are limited to the masonry and the adjacent electrical systems.
Key parties involved: property manager (representative), manufacturing tenant, plant manager, claims adjuster retained by the insurer, building damage estimator, and engineer.
2. The Real Problem
The building is leased to a globally recognized manufacturing company, whose main production machine is located right next to the damaged wall. This machine produces approximately $400,000 worth of parts per day.
In a standard case, we would have simply cleared the workspace and shut down the machinery for the duration of the repairs. Here, a 10-day production shutdown would have resulted in approximately $4 million in losses for the tenant—a risk no one was willing to take.
The real challenge, therefore, was not the technical feasibility of the work, but how to carry it out without ever disrupting production.
3. The Pressure
From the very first visit, the plant manager anticipated a production shutdown and put pressure on the property manager. The tension eased as soon as Bélisle proposed a plan that would allow the machine to keep running.
The factory also imposed strict safety and confidentiality requirements: health and safety certifications and training for all workers, as well as tight access controls, since the parts being produced are confidential.
The constant risk: a delay in material delivery or a labor shortage would have derailed the entire initial plan, since every night of work was meticulously planned.
4. The Project
First step: a site visit with the mason and the electrician, followed by a detailed budget proposal submitted to the insurer for approval. Once the contract was confirmed, a precise schedule was drawn up and the trades were coordinated.
Work took place exclusively in the evenings and at night. Every evening: setup, installation of temporary partitions, demolition of a section of the wall and partial reconstruction, followed by teardown and a thorough cleanup before employees arrive the next morning.
Since a large portion of the factory’s electrical system ran along the wall to be demolished, a temporary electrical system was installed to ensure that all equipment remained operational throughout the duration of the project.
The property manager benefits from a single point of contact for the entire project: daily site visits by the project manager, daily written updates on progress, and a comprehensive photo report upon project completion.
5. Unforeseen Circumstances
The main risk identified from the outset: a delay in the delivery of materials or a shortage of labor, which would have derailed the entire schedule for the nighttime work.
This risk was anticipated and managed in advance—every possible scenario had been taken into account before construction began. Result: no unforeseen scope of work, no delays.
6. The Result
Reconstruction: Masonry wall and electrical systems redone; structure verified as intact by the engineer
Tenant’s operations: Never interrupted—no shutdown of the main production line
Execution: Work carried out entirely at night, with no impact on daytime operations
Coordination: Property manager, tenant, plant manager, insurer, and engineer all aligned on a single schedule
Incidents: None
“We worked in the evening, did our work, then packed up and cleaned up before the employees arrived. The next day, part of the work was already completed without them even realizing it.”
— Maxime Bélisle, Project Manager