A truck crashed into an industrial building, causing a section of the masonry wall to collapse just a few feet from the machinery that produces $400,000 worth of parts per day for the tenant. An engineer confirms there is no structural damage. Bélisle prepares a detailed plan for the nighttime work, has it approved, and then carries out the work night after night, without ever interrupting production or causing a budget overrun.

Type of incident: Structural damage—vehicle impact against an exterior masonry wall

Sector: Industrial (commercial lease)

Scope: ~100 linear feet by 40 feet high of masonry, adjacent electrical systems

Claim value: ~$100 000

Structural validation: Confirmed by a commissioned engineer—no damage to the building’s structure

1. Background

A 53-foot truck collided with an industrial rental building, causing part of the exterior masonry wall to collapse. The loss is estimated at approximately $100,000: about 100 linear feet of wall, 40 feet high, plus the electrical panels and wiring located on the interior of that wall.

An engineer was retained from the outset to confirm that the structure was not affected. Bélisle’s scope of work was therefore limited to the masonry and adjacent electrical systems—a clearly defined scope established even before work began.

Key stakeholders: property manager, manufacturing tenant, plant manager, claims adjuster, property damage estimator, and engineer.

2. The Real Problem

The damaged wall is located directly adjacent to the tenant’s main production line, which generates approximately $400,000 worth of parts per day. A standard 10-day production shutdown would have resulted in approximately $4 million in losses for the tenant.

The complexity of the case is therefore not technical; it is a matter of execution. For the claims adjuster, the challenge is to ensure that a realistic, costed, and approved plan allows the work to be completed without exposing the case to unplanned cost overruns related to a production shutdown.

3. The pressure

Precise coordination is required from the outset: any issues with material delivery or labor availability would have derailed the initial plan, posing a direct risk of schedule and cost overruns.

The factory imposes strict security and confidentiality requirements (accreditations, access control) since the tenant is a globally recognized company whose manufactured parts are confidential—an additional constraint that must be incorporated into the execution plan.

4. The Project

Bélisle visits the site with his mason and electrician, then submits a detailed budget proposal to the insurer for approval before any work begins. Once the estimate is accepted, a precise schedule is drawn up and communicated to all parties.

Work is carried out exclusively at night: setup, phased dismantling of a section of the wall, reconstruction, teardown, and cleanup—each evening, before employees arrive the next day.

A temporary electrical system is installed to keep all equipment operational while the original system, housed in the wall, is dismantled and then rebuilt.

Progress is documented at every stage: daily site visits, daily written progress updates, and a comprehensive photo report provided upon completion of the work.

5. Unforeseen Circumstances

The main risk identified in advance: a delay in material delivery or a labor shortage, which would have derailed the nighttime schedule and generated additional costs.

This risk was anticipated in the initial plan—no unforeseen issues arose during construction. Result: no unaccounted-for scope of work, no deviations from the approved estimate.

6. The Result

Repair:Masonry wall and electrical systems redone according to the approved estimate

Budget Variance: None—initial plan fully adhered to

Business continuity: Tenant’s operations were never interrupted

Documentation: Daily written progress reports, comprehensive photo documentation

Incidents: None

“Every possible scenario had been taken into account before construction began. We didn’t encounter any surprises along the way, and we truly managed the work as we should have.”

— Maxime Bélisle, Project Manager