A sewer backup affected 17 units in a rental building, 9 of which were occupied by uninsured tenants. Bélisle structured the case in two phases to comply with the coverage limits for insured tenants, while avoiding a relocation crisis for the others. Result: the initial estimate of $450,000 was met, with no budget overruns.
Type of claim:Sewer backup (root intrusion)
Sector:Residential rental, 17 units in a 36- to 48-unit building
Scope:Case structured in two phases; 9 uninsured tenants out of 17
Claim value:Approximately $450,000
Coordinated parties:Endependent claims adjuster, building damage estimator, maintenance manager, president of the property management company
1. Background
Tree roots pierced the sewer line of a low-income rental building, causing a sewer backup in 17 units. Nine of the affected tenants do not have personal insurance, which complicates the usual management of a claim of this magnitude, estimated at approximately $450,000.
2. The Real Problem
Typically, a claim of this type is resolved through the simultaneous removal of personal property from the affected units, covered by the tenants’ respective insurers. In this case, nine tenants had no one to cover the cost of their evacuation or relocation. The real risk was that the eight insured tenants would reach their coverage limit for temporary relocation if the first phase’s timeline were to be extended.
3. The Pressure
The deadline set for the first phase—covering eight units—was three weeks. Bélisle, acting as project manager, kept the pressure on the schedule, knowing that any delay would have direct consequences for the tenants’ insurance coverage in this phase.
4. The Intervention
The project was structured into two distinct phases. Phase 1 focused on the eight units occupied by insured tenants, whose personal belongings were handled by their respective insurers. Once these units were delivered, the nine uninsured tenants simply moved their belongings into the renovated units—a simple move rather than a relocation.
The work process followed a rigorous sequence: initial site visit, emergency demolition to limit further damage, joint site visit with the estimator to produce a representative cost estimate, validation of this estimate with specialized suppliers prior to approval, followed by contract signing and ordering of materials. The final schedule was built around the material delivery dates to avoid any discrepancies between the announced timeline and the actual progress on-site.
Progress was tracked via weekly emails—sent every Friday—with photos and status updates for all stakeholders, in addition to site visits every 48 hours and occasional follow-up calls.
5. Unforeseen Issues
When the flooring was removed, the concrete slab was found to be crumbling and had to be scarified and re-leveled before the new flooring could be installed. This unforeseen issue, which was unrelated to the covered loss, was handled directly with the client and resolved before construction officially began; therefore, it had no impact on the estimate approved by the insurer or on the project timeline.
6. The Result
Timeline: Phase 1 completed in three weeks; no insured tenant reached their coverage limit
Costs: Initial estimate of $450,000 fully adhered to
Coordination: Documented weekly reports (photos, progress) sent to all stakeholders
Benefit for the claims adjuster: A phased approach that avoided any additional pressure on coverage limits, without ever deviating from the approved estimate
“I make sure to control costs before construction begins by soliciting bids from my suppliers to stay within the budgets set by the insurance company.”
Maxime Bélisle, Project Manager